Implementation and Commissioning of the 138KV Barra Grande LT Span
The Barra Bonita Substation, operated by CTEEP, operates in the 138kV voltage class and is undergoing a process of implementing two new spans, with the installation of Siemens Siprotec 5 IEDs in the protection system.
In collaboration with Siemens, CCESE carried out the following activities at the substation, in the Barra Grande Transmission Line span:
Commissioning of the Protection System.
Carrying out Functional Tests on the new protection system with yard equipment.
Protection Function Characteristics Tests
Control Tests at Levels 0, 1, 2 and 3
Validation of Control and Protection Logics and Interlocks
Point Ascent Tests for SCADA.